Current Projects/Updates:
- Mills Property Management New Office Building
- Brookings Elder Housing – Ron Kramer & Crew - Drywall will be finished up this week with painting to follow. Acoustical ceiling grid has started in the South wing. Flooring is almost complete in all the rooms leaving only the public rooms and hallways left to finish. Wallpaper has been back-ordered for over a month on this project causing the schedule to be pushed back. The deadline for the first walkthrough is April 8th, 2008.
- BHS Track Expansions - Brian Schmidt & Crew - This project has been on hold through the winter, but should be starting up again within the next month. Work will start on the Football Storage building as soon as possible, and then continue with the other 3 track buildings, and the bleacher foundation system.
- Rustic Hills Community Church, Sioux Falls - Jerry Ehlebracht & crew, Tim Mulvey & crew -
Jerry & crew has completed installing the steel roof on the Sanctuary. Currently they are working on installing steel stud framing, steel roof trusses, and roof sheathing. In the next few weeks, they will also be working on the steel roofing, and steel siding. Subcontractors will also begin the masonry work and underground rough-ins once the weather shapes up a little bit.
- Adee Honey Farms – Greg Kastner & Crew; Tom Sheeley & Crew - On this project we are installing the roof steel, the ceiling liner panel, the wall liner panel and the roof/wall insulation all at the same time to create additional fall protection while installing the roof. We have 2/3 of the building completed for all of these items. We will start the interior framing next week. Everything is on track and going well.
- MeadowGreen - 1449 SOG – Larry VanBallegooyen & Crew - Another unit has been sold and the customer is in the selection progress. The electrical walk-through is complete and the electrician is starting to run wires.
- MeadowGreen - 1449 SOG – Larry VanBallegooyen & Crew - This unit is in the finishing stages. The cabinets are here, the doors and trim are going on and we have a homeowner that is excited about making the move to MeadowGreen.
Work Orders:
- Indian Hills Bike Path Bridge - Brian Schmidt & Crew – The foundation for the bridge is complete. The pre-manufactured bridge should arrive by the end of the month so we can set it in place, and finish the sitework. Site conditions have been less than ideal throughout most of this project, but Brian and his crew are doing a great job.
- Colony West Canopies – Chris Christopherson, Brian Schmidt & Crews - This project consists of building 46 wood framed entrance canopies for an apartment complex in Watertown. Chris and crew completed all of the framing. Currently, Brian and crew are installing the roof steel and fascia.
- Fergen’s (Former Space) Remodel - Chris Christopherson & Crew - This project consists of remodeling the downtown Fergens store into new offices. Currently, we are concentrating on the north half of the building. Joe and crew started up the project and completed much of the demolition, as well as framing and drywall. Chris and crew have since taken over, and continue to make progress on the framing and drywall. We hope to get started on the south half soon, and are shooting for an April project completion.
|