Mills Construction

  Who We Are
What We Do
Current Projects
Foresight Surveyors
Job Opportunities
Links
News/Interest
Contact Us
Home
 

1703 Howard School Remodel  Randy Scholl & Crew  Demolition is complete in all areas of the project and interior finishes are under way in all rooms of the project. Cabinets and countertops are currently being installed in the Science and FACS labs. The boy’s locker room is nearing completion with lockers and carpet being installed next week. Tile work is ongoing in the girl’s locker room and will also have lockers and carpet installed next week.  This project is scheduled to be completed in early September.

1702 HD Electric, Clear Lake  Brian Schmidt & Crew  Brian & crew have finished the foundation and have been working on the tie bars, sand / oil separator pits, and corefloor.  Last week we unloaded 10 semis that were loaded with our metal building.  Underground will be wrapping up in the office this week with concrete floor following shortly after.  The warehouse will be brought up to grade soon and then we will start prepping that for in-floor heat.  Great job at getting the foundation done ahead of schedule!

1701 GracePoint Wesleyan Church Jerry Ehlebracht & Crew The concrete footings and foundations are all complete except for the entrance area into the building. The first pour of the concrete floor is ready and the second will occur shortly after the first. The crew has been installing the structural steel for the second floor and roof structure. The bar joists will be showing up next week. The project is beginning to take shape.

1700 Dakotaland Federal Credit Union Huron  Office Crew This project is a 30,000sf office building for DFCU. Mills Construction is doing all the plans and specs for this project and will also serve as the Construction Manager. We do not plan to have any crew on site doing any of the work. Greg Kastner will be managing the project on site and Paul Sahr will be managing the project from the office. Angie Boersma has been pushing hard to wrap up the architectural plans along with all the engineering plans. We are putting together the first set of Bid Packages to be bid out soon. The project is scheduled to start within the next three weeks.

1699 Dakotaland FCU Watertown  Darin Dobrenski and Crew  This new project is a 7,445 SF wood framed, two story credit union building.  There is about 5,260 SF on the main level, consisting of offices, conference rooms, teller lanes/drive-up, restrooms, and tenant spaces.  The second level is 2,185 SF and includes a conference room, mechanical room, IT room, and storage closets.  This project is located on the corner of highway 212 and 11th St., where the existing Goodyear Watertown Tire building is located.  Demolition of the existing structure will get underway this week and excavation of the footings will follow.  Completion is scheduled for April 2018.

1698 Slydog, Madison  Randy Scholl & Crew The pump room and dividing wall are completed. Flooring will start next week with the trim and doors following.

1697 SDSU Performing Arts Center  Nick Chaney & Crew  We are on site doing some window blocking and we are installing HM door frames ahead of the block layers.  Next week we will be able to start the roof blocking on the south half of the project.  The glue lams are showing up right after Labor Day.

1694 SDSU Plant Science Greg Kastner & Crew The crew is putting the finishing touches to this project. The final walkthrough was yesterday. There are still a handful of changes yet to complete so the crew will be on site at least through the end of the week wrapping up these changes and the punch list items. The project is looking great and the Owner has an open house at the end of the month. We look forward to great accolades in regard to the quality and workmanship that our crews produced on this project.

1690 Millborn Seeds Seth Skinner & Crew Work continues on grading and pouring the interior concrete floors, which should be about 75% complete by the end of the week.  Most of the steel siding on the south side has been installed, and window installation should begin this week.  The mezzanine concrete floor is in place and steel stud framing is underway.  Bowes will be onsite later this week to begin final grading, subgrade prep, and base course.

 

1689 Brookings Hospital Expansion, Carpentry Package Ron Kramer & Crew  Ron & Crew just finished demoing out the old outreach walls and roof last week.  This week will be a lighter week for us as we are waiting on other trades.  Next week we will start installing the metal panels on the donor wall.  Installation of doors, hardware, and cabinets are ongoing as they become available to us.  The main entry is coming together with most of the framing done and it should be open sometime in October.  We will start demo in the north radial in early September.

 

 

The Landing 

Larry VanBallegooyen & Crew

 

7207  2126 & 2128 Goldenrod Trail.

This twin home will be a Voyager floor plan with a sunroom in one unit and a walk out bay in the other. Excavation is complete and the foundation will be poured next week.

 

7206 2122 & 2124 Goldenrod Trail.  

2124 This spec unit is finished and is ready for sale.

 

7110 2133/2135 Goldenrod Trail

This twin home will have a Mariner floor plan with concrete patios. Framing of the exterior walls has begun and the trusses will be set next week. Both sides of the twin home are sold and closings are scheduled in September and October.

 

7108 2125 & 2127 Goldenrod Trail.

This twin home is the Grand Mariner layout. Both units in this building are nearing completion. Flooring, cabinets and trim are installed in 2125 Goldenrod Trail and the final items will be completed next week. The cabinets, doors and trim are currently being installed in 2127 Goldenrod Trail with the completion date set for August 25th.

 

 

 

 

 
 
1311 Main Ave. South
Brookings, SD 57006
P: 605.697.3100
F: 605.697.3131
info@buildwithmills.com

 

 
Copyright Mills Construction

 

 

Web Site Designed by: MAS Media