Option 1

Address:
Option 1
Brookings, SD

Superintendent: Joe Sneve & Will Weeks

SF:
Owner: Option 1
Architect: Mills Construction
Delivery Method: Design/Build

This small project includes remodeling a former salon space for use by Option 1. This project is small but still has had a fair amount to it. This project started in mid February with the demolition we needed to do and has progressed to the point that painting will be taking place next week. Final trim-out will be the week after.